5E Advanced Materials expects power initiative to cut operating costs by $8 million to $9 million
FEAM•
FEAM•5E Advanced Materials expects its power initiative to reduce annual operating expenses by approximately $8 million to $9 million, with about $500,000 in capital spending. It targets annual V-BOR production of approximately 100,000 short tons, up from an annualized 82,000 short tons.
5E Advanced Materials expects its power initiative to reduce annual operating expenses by approximately $8 million to $9 million, requiring approximately $500,000 in capital. The company is targeting reduced grid reliance by next summer and plans to order a capacitor by January. Annual V-BOR production is targeted at approximately 100,000 short tons, compared with the current annualized rate of approximately 82,000 short tons; a January SAC plant restart is intended to improve output.
V-BOR sales volumes are expected to rise through November and December, following October sales of approximately 2,500 tons at a $767-per-ton netback.