78% of data center operators report electrical disruptions, Fluke study finds
FTV•
FTV•A Fluke study found that 78% of data center operators experienced electrical or power-system disruptions over the past year, while 33% reported full readiness for AI data center expansion.
Electrical or power-system issues disrupted operations, delayed projects or caused serious near-misses at 78% of operators over the past year. Power-quality problems limited AI or GPU workload deployment or operation for 29%, and just 45% had real-time visibility across critical electrical systems.
Insufficient power and grid capacity constrained expansion for 76% of operators, with additional connections or capacity taking an average of 12 months. Electrical skills shortages delayed upgrades or new capacity for 34%, and 60% reported greater difficulty recruiting qualified electrical technicians.