Anfield wins Utah concept approval for Velvet-Wood water treatment plan in dewatering push
AEC•Treated discharge targeted for November
Treated discharge targeted for the second week of November, with a November 7 start date flagged, pending final sign-off and permit compliance.
Pumping timeline and hub-and-spoke strategy
Active pumping expected to dewater the remaining decline within about one month, with existing underground workings taking roughly two to three months.
Milestones support a hub-and-spoke strategy centered on the fully permitted Shootaring Canyon Mill in Utah.
Wastewater outfall reactivation request filed
Formal request filed to reactivate the site’s permitted wastewater outfall, a step needed to begin treated-water discharge.
Utah concept clearance advances Velvet-Wood restart
Anfield Energy secured Utah water-quality concept clearance for its Velvet-Wood water treatment plan, advancing restart of the uranium-vanadium mine.