Anthropic's Australian data centre overwhelmingly opposed by residents
ANT•
ANT•A filing showed that 595 of nearly 600 submissions on a planned Australian data centre opposed the project or sought a delay; two supported it and one was neutral. The facility, with Anthropic as anchor tenant, is planned for a 1.44-gigawatt computing load.
A filing for the proposed Western Downs Digital Park, about 250 km west of Brisbane, showed that 595 of nearly 600 public submissions opposed the data centre or asked for a delay until environmental hurdles were addressed. Two submissions supported the project and one was neutral.
Objectors raised concerns about water use, electricity demand and prices, noise, road damage from construction traffic and pressure on housing. The project is planned on farmland and would have a computing load of 1.44 gigawatts, making it one of Australia's biggest data centres.