Aura Minerals says Era Dorada project stays on schedule with 60% earthmoving complete
AUGO•Era Dorada project update
Aura Minerals reported Q2 2026 progress at its Era Dorada mining project in Guatemala, citing 60% completion of earthmoving work.
The company said the project plan includes a closed water circuit to reuse 100% of process water, with approved capex to deliver potable water to the region.
Build-out remained on schedule, with US$ 15.3 million invested in 2026 and 366 employees as of June.