Azio AI completes Power Champion infrastructure at Atlas One, awaits GPU delivery
AZIO•
AZIO•Azio AI completed Power Champion infrastructure at Atlas One and was awaiting GPU delivery as of Nov. 25, 2026. The 10 MW hosting contract carries about $90 million in capacity reservation charges over 60 months, but no capacity has been energized and no revenue has been recognized.
Azio AI said it completed Power Champion infrastructure at Atlas One and was awaiting GPU delivery as of Nov. 25, 2026. No Power Champion capacity has been energized, and no revenue has been recognized under the agreements.
The 10 MW hosting contract carries approximately $90 million in capacity reservation charges over 60 months, payable only on delivered, energized capacity. Expansion rights could raise capacity to 50 MW and charges to approximately $450 million; none have been exercised.
A separate, non-additive GPU sales pipeline totals approximately $307 million for up to 512 NVIDIA HGX B300 systems. The pipeline does not represent purchase orders.