Baker Hughes to Provide LM6000PF Compressors and NovaLT16 Generators for 8.4 MTPA Offshore LNG Terminal
Baker Hughes will supply two LM6000PF gas turbine-driven compressor trains and three NovaLT16 turbine generator packages for ST LNG’s proposed 8.4 MTPA offshore export terminal. The initial phase is expected to deliver 2.1 MTPA with first LNG targeted for Q2 2030, supporting the project’s FID progression.
1. Contract Award and Scope
Baker Hughes signed an agreement to supply critical gas compression and power generation technology for ST LNG’s proposed 8.4 MTPA offshore U.S. LNG export terminal, securing the core equipment package for the project’s first 2.1 MTPA phase.
2. Equipment Provided
The scope includes two LM6000PF aeroderivative gas turbine-driven centrifugal compressor trains and three NovaLT16 gas turbine generator packages, ensuring both production capacity and power generation for the initial liquefaction unit.
3. Development Timeline
The first phase is targeted to deliver 2.1 MTPA with first LNG expected in Q2 2030, while ST LNG moves toward Final Investment Decision and Baker Hughes anticipates recognizing orders as the project advances.