Copel presents hydropower expansion projects with about R$ 2.6 billion in annual contracted revenue
ELP•Copel secured 2,100 MW of hydropower expansion projects in the 2026 capacity auction, with construction underway and about R$ 2.6 billion in expected annual revenue under 15-year contracts starting in 2030.
1. Hydropower expansion
Copel secured 2,100 MW of hydropower expansion projects in the 2026 capacity auction, and construction is underway. The projects are expected to generate about R$ 2.6 billion annually under 15-year contracts starting in 2030.
2. Additional projects and assets
Salto Caxias is registered for the next capacity auction with 900 MW of additional capacity. Pumped-storage hydropower projects under development total approximately 9,000 MW. The 2026 distribution tariff review established a R$ 19.9 billion net regulatory asset base, 11% above net book value.