Danieli wins ArcelorMittal order for electric steelmaking project in Dunkirk
MT•ArcelorMittal selected Danieli to supply a 300-ton electric arc furnace for its €1.3 billion electric steelmaking project in Dunkirk, France. The facility is scheduled to start up in 2029 and have annual production capacity of 2 million tons.
1. Furnace order
ArcelorMittal selected Danieli to supply an electric arc furnace for its Dunkirk steelmaking site in France. The order supports a €1.3 billion investment, with startup scheduled for 2029.
2. Project details
The furnace will have a 300-ton tapping capacity and annual steel production capacity of 2 million tons. Danieli’s supply includes fume treatment, material handling systems, and a complete electrical and automation package. The facility is expected to produce steel with three times less CO2 than the blast furnace route.