Endeavour Silver outlines growth plans in corporate presentation
EXK•Kolpa integration and Pitarrilla update
Peru’s Kolpa integration was highlighted. In Q2, the operation processed 233,408 tonnes at 2,565 tpd, producing 1,184,457 AgEq ounces.
Endeavour said a Pitarrilla feasibility study is expected in Q3 2026, and described the project as a large undeveloped silver resource with 694 million AgEq ounces.
Growth strategy centers on Terronera ramp-up
Endeavour Silver outlined a growth-driven strategy as it ramps up Terronera, its newest silver-gold mine in Mexico.
Production guidance was lifted to 14.6 million to 15.6 million silver-equivalent ounces (AgEq) for 2026, compared with 11.2 million AgEq ounces in 2025.
The company said the Terronera ramp-up is targeted through Q3 2026. Q2 output was 1,298,268 AgEq ounces at 1,931 tonnes per day (tpd).