Endeavour Silver resumes Terronera operations after August blockade suspension
EXK•Endeavour Silver said a blockade suspended Terronera operations from Aug. 12 to Aug. 24, 2026, reducing third-quarter throughput to 165,171 tonnes from 175,729 tonnes in the second quarter. The company expects full-year production to be at or slightly below the low end of guidance and is recalculating its production and cost outlook.
1. Mine operations and repairs
Terronera operations have resumed after a blockade suspended the mine from Aug. 12 to Aug. 24, 2026. Guanaceví’s mill was taken offline on Sept. 21 to replace its primary mill head and trunnion; repairs are expected to finish in the first half of October, with processing continuing at lower throughput.