Enerflex wins contract for over 1 GW of behind-the-meter gas power units for North American data center project
EFX•Enerflex won a contract to supply more than 1 gigawatt of behind-the-meter natural gas-fired power units for a North American data center. Its backlog for this type of generation rose above 1.75 GW, and the company authorized about $100 million to expand Engineered Systems capacity.
1. Contract and backlog
Enerflex won an Engineered Systems contract to supply more than 1 gigawatt of behind-the-meter natural gas-fired power units for a North American data center. Its backlog for behind-the-meter gas-fired generation rose above 1.75 GW, including about 450 megawatts announced on Oct. 1, 2026. Deliveries are scheduled through 2028, supported by North American manufacturing operations.
2. Capacity expansion
Enerflex authorized about $100 million to expand Engineered Systems capacity, including $15 million in 2026 capital expenditure guidance.