Fortuna Mining approves $109 million Séguéla plant expansion, targets over 200,000 ounces annually from H2 2028
FSM•Fortuna Mining approved a $109 million expansion of its Séguéla processing plant, targeting annual gold output above 200,000 ounces from the second half of 2028. The expansion would increase annual throughput by 30% to 2.3 million tonnes.
1. Séguéla expansion
The board approved a $109 million expansion of the Séguéla processing plant, increasing annual throughput by 30% to 2.3 million tonnes. Commissioning is scheduled for Q3 2028, and the expanded plant is expected to support annual gold output above 200,000 ounces from H2 2028.