Hallador Energy posts transcript of Q2 2026 earnings call
HNRG•Quarterly results and outlook
Q2 results: net loss of USD 15.2 million; adjusted EBITDA of -USD 2.9 million; revenue of USD 101.5 million; capex of USD 26.3 million tied to Merrim outage upgrades.
Forward sales book rose to USD 2.4 billion on a segment basis; DOE support is seen for Merrim upgrades, not for Turtle Creek.
Earnings call transcript and project updates
Hallador Energy hosted its fiscal Q2 2026 earnings call with Chairman and CEO Brent Bilsland, CFO Todd Tellez, analysts, and an IR adviser.
Management cut Turtle Creek Gas project cost guidance to below USD 800 million, pegging it near USD 1,700/kW; COD shifted to 2H 2028.
Turbine disassembly is underway with Siemens; equipment shipment is still expected in September; MISO ERAS interconnection results are due mid-August, targeting FID in September.