Hochtief unit UGL wins Neoen, Tesla contract for Goyder Battery Stage 2 in South Australia
TSLA•Timeline for site works and operations
Site works start in August 2026; operations targeted for 2028.
UGL wins contract for Goyder Battery Stage 2
Hochtief unit UGL won a contract from Neoen, Tesla to deliver Stage 2 of the Goyder Battery in South Australia.
Stage 2 adds 227 MW/907 MWh, lifting total project capacity to 454 MW/1,814 MWh.
UGL scope covers balance-of-plant civil, electrical, high-voltage works for Tesla Megablock, testing, commissioning.