Imperial Oil Says Continued Construction Of The Enhanced Bitumen Recovery Technology (Ebrt) Pilot With Start-Up Anticipated By 2027 - Conf Call - IMO News | Rallies
Imperial Oil Says Continued Construction Of The Enhanced Bitumen Recovery Technology (Ebrt) Pilot With Start-Up Anticipated By 2027 - Conf Call I IMO • 2026-07-31 EBRT pilot, turnarounds and Kearl production updates
Imperial Oil says continued construction of the enhanced bitumen recovery technology (EBRT) pilot with start-up anticipated by 2027 - conf call
Imperial Oil expects Strathcona turnaround to rank first quartile versus industry for cost and duration - conf call
Imperial Oil says next planned turnaround is not until 2029 - conf call
Imperial Oil says Kearl flotation column production start-up expected in Q4 2026 - conf call
Imperial Oil expects higher Kearl production in H2 2026 via increased throughput - conf call
Imperial Oil expects first production from Kearl's East Pit in November/December 2026 - conf call
Rail capacity, refinery downtime and downstream outlook
Imperial Oil will add additional rail handling capacity to alleviate that congestion and are targeting completion by year end - conf call
Imperial Oil says Nanticoke refinery experienced unplanned downtime impacting crude units; to resume full operations by early August - conf call
Imperial Oil says downstream outlook remains positive for rest of year on higher volumes, structural advantages - conf call
Imperial Oil notes tightness in refined product markets - conf call
Imperial Oil expects further unit cost reduction in 2026, targets $18/barrel in 2027 - conf call
Imperial Oil says it is also seeing strong value across distillate products more broadly, not just renewable diesel - conf call