Intel has entered mediation with Tower Semiconductor after indicating it won't proceed with a 300mm wafer production contract at its New Mexico facility that was signed in September 2023. Production flows initially qualified at Tower’s Fab7 in Japan have been redirected back there for continued customer support as Intel pauses the arrangement.

1. Contract Background

Intel and Tower Semiconductor signed a September 2023 agreement for Intel’s New Mexico facility to produce 300mm wafers for Tower’s customers, marking Intel’s entry into contract manufacturing for Tower’s silicon photonics and SiGe products.

2. Intel Withdrawal and Mediation

Intel recently indicated it will not move forward with the New Mexico contract, triggering a formal mediation process between the two companies to resolve disputes over the unfulfilled production agreement.

3. Operational Redirection

Wafer production flows that had been transferred or were in qualification at the New Mexico site are now being redirected to Tower’s Fab7 facility in Japan, ensuring continued support for customers during the pause in Intel’s involvement.

4. Implications for Intel Foundry

The contract suspension may delay Intel’s foundry expansion strategy and heighten reliance on external foundry partners, while customers may seek longer-term assurances before committing capacity beyond existing reservations.