Lithium Americas raises Thacker Pass Phase 1 capital cost estimate to US$3.83 billion
LAC•Lithium Americas raised its Thacker Pass Phase 1 capital cost estimate to US$3.83 billion from US$2.93 billion, including contingency, and increased fiscal 2026 capital spending guidance to US$1.7 billion–US$2 billion.
1. Higher project estimate
Lithium Americas raised the Thacker Pass Phase 1 capital cost estimate to US$3.83 billion from US$2.93 billion, including contingency. Mechanical completion remains targeted for late 2027, with production ramp-up expected through 2028. Incremental funding needs total approximately US$995 million, including US$650 million expected from company contributions that would increase its joint-venture stake, US$315 million from DOE loan reserves and US$30 million from reduced reserve requirements. Fiscal 2026 capital spending guidance increased to US$1.7 billion–US$2 billion from US$1.3 billion–US$1.6 billion.