LS Power says permitting, grid connections constrain new US power supply
XLU•LS Power CEO Paul Segal said permitting and grid connections, rather than capital shortages, constrain new U.S. power generation. Gas plants can take five years to develop, compared with one to two years for data centers.
1. Supply bottlenecks
LS Power CEO Paul Segal said permitting and grid connection bottlenecks, not capital shortages, constrain new U.S. power generation. Billions of dollars in private capital are available for projects that have permits and are ready for financing.
2. Different development timelines
Gigawatt-scale gas plants take five years to develop, compared with one to two years for data centers, creating a timing mismatch between supply and demand. PJM faces increasing capacity shortages as demand rises, while Texas remains well supplied after rapid additions of wind, solar and battery storage.