New Found Gold presents three-phase development plan for Queensway Gold Project
NFGC•New Found Gold outlined a fully funded development plan for Queensway with total funding of CAD 290 million. Phase 1 requires CAD 150 million, with Pine Cove processing planned to start in the fourth quarter of 2027 and a new Queensway mill planned to begin operating in 2031.
1. Queensway development plan
New Found Gold outlined a fully funded plan to advance the Queensway project, with total funding of CAD 290 million. Phase 1 requires CAD 150 million in capital, and processing at Pine Cove is planned to start in the fourth quarter of 2027. Pine Cove capacity is targeted to double to 1,400 tonnes daily by the second half of 2027; a new Queensway mill is planned to begin operating in 2031 with capacity of 4,900 tonnes daily.
2. Production projections
Queensway’s projected total gold production is 1.7 million ounces, with average annual all-in sustaining costs of USD 1,375 per ounce.