Nexa Resources Resumes Atacocha Mine After 0.9 kt Zinc Production Loss
Operations at Nexa Resources' Atacocha San Gerardo open-pit mine resumed on February 16 after the Joraonivoc community released the access road, with capacity utilization gradually recovering. The company estimates a 0.9 kt zinc production loss from the disruption, expects full recovery in coming months and keeps its 2026 production guidance unchanged.
1. Operations Resumption at Atacocha Mine
Operations at the Atacocha San Gerardo open-pit mine restarted on February 16 after access was restored by the Joraonivoc community. The site is gradually ramping up toward normal capacity utilization in line with standard operating procedures.
2. Production Loss Estimate and Guidance Impact
Due to the road blockage, Nexa Resources estimates a temporary 0.9 kt zinc production shortfall. Management expects to recover the lost volume over the coming months and confirms that 2026 production guidance remains unchanged.
3. Community Engagement and Safety Protocols
Nexa emphasizes ongoing dialogue with host communities and prioritizes employee and contractor safety. All activities at Atacocha are conducted under strict safety protocols and the company reaffirms commitment to social development initiatives.