Nexans completes subsea cable installation for Chevron’s Jansz-Io project
CVX•Nexans completed installation and burial of a 145 kV subsea cable for Chevron Australia’s Jansz-Io Compression project in October 2026. Cable connections and rock placement remain before commissioning, with the final energization test planned for February 2027.
1. Cable installation completed
Nexans completed subsea cable installation and burial for Chevron Australia’s Jansz-Io Compression project in October 2026. The 145 kV dynamic cable spans approximately 135 km between Barrow Island and a floating control station; installation included 26 buoyancy modules, and 30 km of cable was buried.
2. Work remains before testing
Cable connections and rock placement along the final 28 km remain outstanding before commissioning. Chevron Australia plans the final energization test for February 2027.