NexGen Energy publishes corporate deck outlining Rook I uranium project construction progress
NXE•Rook I construction progress and project plan
NexGen Energy outlined construction progress at its 100%-owned Rook I uranium project in Saskatchewan following a federal license to construct.
- The 2021 feasibility study mine plan remains the base case, targeting up to 30 million lbs of U3O8 per year in years 1-5.
- The project is positioned to supply about 20% of global uranium from a single mine, based on feasibility study production assumptions.
- The contracting strategy targets delivery-time market pricing; sales commitments total 10 million lbs with 2 million lbs annual deliveries from commercial production.
- Arrow deposit reserves were cited at 239.6 million lbs grading 2.37% U3O8; measured and indicated resources total 256.7 million lbs.