North Sea gas maintenance schedule adds Visund outage
UNG•The maintenance schedule added a Visund gas production outage from Nov. 5 to Nov. 16, affecting 13.2 million cubic metres per day.
1. Visund outage added
The schedule lists a Gassco outage at Visund from Nov. 5, 0600 CET, to Nov. 16, 0600 CET, with 13.2 million cubic metres per day unavailable because of gas production field unavailability.