Olenox mines 15.13 bitcoin in July 2026 operating update
OLOX•July 2026 bitcoin production and fleet update
- Olenox reported July 2026 bitcoin production of 15.13 BTC, credited to its mining pool accounts.
- Average operational hashrate reached 1.02 EH/s, equal to 64% of the fleet’s economic capacity due to summer curtailment.
- Installed fleet totals 9,584 S21-class ASIC miners, about 35 MW of capacity, representing 2.19 EH/s nameplate at 16 J/TH efficiency.
- Output came from third-party hosting on the ERCOT grid; the sub-$0.02 per kWh gas-to-compute strategy was not reflected.