Oracle-backed expert backs Project Jupiter fuel-cell microgrid plan, citing 92% cut in NOx emissions
ORCL•
ORCL•The design change is projected to cut nitrogen oxide emissions by about 92% versus the prior plan, easing pressure on the Paso del Norte airshed.
The project would avoid public drinking water for cooling or fuel-cell operations; ongoing water use is estimated at 168,000 gallons a year.
Oracle has committed $50 million to local water and wastewater infrastructure in Doña Ana County, with about 80% funded.
Oracle backed an updated energy plan for Project Jupiter that targets lower air emissions, reduced water use and reliable data center power.
An external environmental-health review supported an air-permit application for a fuel-cell microgrid, replacing prior natural-gas turbines and diesel backup generators.