Polenergia completed foundation installation for 100 turbines and two offshore substations at the Bałtyk 2 and Bałtyk 3 wind farms.
The projects have 1.44 GW combined capacity, marking a key construction milestone ahead of planned first power in 2027.
Full commercial operations are targeted for 2028, with output expected to cover annual demand for more than 2 million households.
Offshore work continues on export cables, substation development, onshore grid connections, turbine installation preparation.