Seabridge KSM project “substantial start” designation faces court-ordered review in British Columbia
SA•Court orders reconsideration of KSM designation
British Columbia Supreme Court ruling on June 8, 2026 ordered a reconsideration of KSM’s “substantially started” designation.
Tsetsaut Skii km Lax Ha challenged the designation, triggering a 90-day consultation process that runs through Sept. 28, 2026.
BC’s Environmental Assessment Office plans to seek Seabridge’s response to submissions, then draft a report for a new decision.