Seondo Electric wins KRW 2.37 billion supply contract with Korea Electric Power
KEP•Seondo Electric signed a KRW 2.37 billion supply contract with Korea Electric Power for switchgear and related equipment at the Guri substation. The contract is 6.21% of Seondo Electric’s 2025 consolidated revenue, with supply scheduled through Sept. 6, 2027.
1. Contract details
Seondo Electric signed the contract on Oct. 26, 2026. It covers 25.8kV eco-friendly switchgear and related equipment for the Guri substation in Gyeonggi Province, with supply running from Oct. 26, 2026, through Sept. 6, 2027.