UL Solutions says rising AI power demand reshapes data center design
ULS•UL Solutions says rising AI power demand is reshaping data center design. Global data centers consumed 485 terawatt-hours in 2025, up 17%, and the International Energy Agency expects consumption to roughly double by 2030.
1. Power and cooling needs
Rising AI power demand is driving integrated power distribution, protection and cooling systems in data centers. A single AI server rack could draw as much peak power as 65 homes by 2027. Emerging 800-volt DC systems require installation-specific fault protection, while maintenance may require de-energization, specialized training and protective equipment. Liquid cooling is expanding into power-delivery equipment, and developers are increasingly adopting prefabricated infrastructure evaluated as integrated assemblies.