Montana Stibnite Hill resumed excavation in late July; 300 tons delivered in 2026; earlier 800 tons at 10% Sb hauled to Radersburg.
Ontario Fostung tungsten plan advanced toward a 20,000-ton bulk sample for beneficiation testing; assays to be run at the Radersburg lab.
Nolan Creek startup target moves toward late 2026
United States Antimony outlined an accelerated push to supply customers with company-mined antimony ore for the first time in 2026.
Nolan Creek Alaska project moved toward late-2026 startup; contractors toured the underground site ahead of mid-August tenders; ore to Radersburg Mill.
Qualified-person report cited inferred reserve of 42,412 tons at 28% Sb, 0.408 oz Au/ton; estimated gross value USD 377 million.