D•US data centers and other large power users can cut grid-related charges by reducing power use during peak-demand hours. A large Texas data center could avoid $33.4 million in transmission costs by staying off the grid for one hour a year, while PJM power-system costs have risen by $29.4 billion.
Data center operators and other large power users can reduce electricity bills by curbing grid use during a handful of peak-demand hours each year, a legal practice encouraged under US power-market rules and state tariffs. Because grid costs are allocated partly based on use during periods of highest demand, a large Texas data center could avoid $33.4 million in transmission costs by staying off the grid for one hour a year, according to NRG Energy.
Critics say peak shaving can let large users reduce their share of grid costs in ways unavailable to households, as power bills rise and AI data centers drive demand for electricity-system expansion. PJM Interconnection’s independent monitor says data center growth has increased power-system costs across the grid by $29.4 billion, with charges paid by utilities and ultimately passed to customers.
The Data Center Coalition says peak shaving reduces demand when supply is tight and can lower costs for all customers by limiting the need for new capacity and transmission. Regulators are considering changes to cost-allocation rules; Dominion Energy said it has created a rate class mostly for data centers, with new facilities required to sign 14-year contracts and make minimum payments if they do not use the power.