WWR•Westwater Resources advanced permitting for its Coosa Graphite Mine in Alabama, targeting completion in June 2027 under FAST-41. Endangered Species Act consultation concluded ahead of schedule, and the Section 404 permit application moved into further review.
1. Permitting advances
Westwater Resources said permitting for its Coosa Graphite Mine in Alabama has advanced, with completion targeted for June 2027 under FAST-41. Endangered Species Act consultation concluded ahead of schedule, and the Section 404 permit application moved beyond public comment into further review.
2. Mine plans and appointment
Coosa is intended to provide natural graphite feedstock for the Kellyton Graphite Plant. Preliminary mine planning studies have begun to evaluate Coosa’s vanadium mineralization for possible inclusion in the mine plan. Anne Duncan was appointed general manager of the mine, effective October 26, 2026.