Artemis Gold expects 2026 AISC at high end of US$925–1,025 per ounce guidance
Artemis Gold remains on track to produce 265,000–290,000 ounces of gold in 2026, but expects all-in sustaining costs at the high end of its US$925–1,025-per-ounce guidance. Year-to-date production was 205,532 ounces at US$1,024 per ounce in all-in sustaining costs.
1. 2026 outlook
Artemis Gold expects 2026 all-in sustaining costs at the high end of its US$925–1,025-per-ounce guidance, citing higher reagent, contractor and diesel costs. It remains on track to produce 265,000–290,000 ounces of gold; year-to-date production reached 205,532 ounces, with all-in sustaining costs of US$1,024 per ounce.
2. Projects and spending
Growth capital spending is forecast at $685 million–$755 million, with Phase 1A and EP2 spending weighted toward year-end. Phase 1A commissioning remains scheduled for December 2026, while EP2 is on track for the second half of 2028.