Centerra Gold forecasts 2026 all-in sustaining costs of $1,650-$1,750 per ounce
CGAU•Centerra Gold forecast 2026 gold production of 260,000-290,000 ounces and all-in sustaining costs of $1,650-$1,750 per ounce. It estimated Thompson Creek’s restart costs at $425 million-$450 million, with first production targeted for mid-2027.
1. 2026 outlook
Centerra Gold forecast 2026 gold production of 260,000-290,000 ounces and copper output of 50 million-60 million pounds. Gold production costs are projected at $1,500-$1,600 per ounce, while all-in sustaining costs are forecast at $1,650-$1,750 per ounce.
2. Mine plans and liquidity
Mount Milligan’s all-in sustaining cost guidance is $1,100-$1,200 per ounce, compared with $1,194 per ounce in 2025. Thompson Creek is targeting first production in mid-2027, with restart costs estimated at $425 million-$450 million; the company said organic growth is expected to be self-funded and reported $998 million in liquidity as of September 30, 2026.