Eni starts gas production at Maha field offshore Indonesia
E•Eni started gas production at the Maha field offshore Indonesia on October 30, with capacity of 250 million standard cubic feet per day. The field brings combined Jangkrik FPU and South Hub production to 750 million standard cubic feet daily.
1. Maha production begins
Eni started production at the Maha gas field offshore Indonesia on October 30, 2026, 21 months after the final investment decision. The field has capacity of 250 million standard cubic feet per day, bringing combined Jangkrik FPU and South Hub production to 750 million.
2. Supply and infrastructure
Two subsea production wells connect to the Jangkrik floating production unit through about 12 kilometers of flowlines. The gas will supply Indonesia's domestic market and the Bontang LNG plant, which serves domestic and export markets. Maha is operated by Searah, a 50-50 joint venture between Eni and PETRONAS.