Erthos breaks ground on 52-MWac Project Bravo solar plant in Texas
LYB•Interconnection, timing and project economics
Interconnection is set at the Conoco 138 kV substation, supplying power behind the meter to the adjacent Matagorda polymers complex.
The target commercial operation date is November 2026.
Project economics include a safe-harbored 40% investment tax credit, including a 10% Energy Community adder.
Project Bravo breaks ground in Matagorda County
Erthos broke ground on Project Bravo, a 52 MWac utility-scale solar plant in Matagorda County, Texas.
The project targets 124 GWh of annual output under a 20-year Private Use Network PPA with Equistar Chemicals, a LyondellBasell unit.