FingerMotion signs binding deal to acquire rights, permits for 9.9 MW Alberta powered land site
FNGR•Project plan and timeline
The plan calls for behind-the-meter generation with on-site power use, avoiding grid interconnection, transmission tariffs, or interconnection queue exposure.
The transaction marks the first acquisition in the Brooks Campus Zone, a planned cluster of separately owned and permitted 9.9 MW sites.
FingerMotion targets a fully permitted site within 120 days of release to work under Alberta Utilities Commission Rule 007.
Binding deal for Alberta powered land site
FingerMotion signed a binding memorandum of understanding to acquire land rights and permitting for a 9.9 MW powered land site in Alberta.
The asset sits in the County of Newell, about 185 kilometers southeast of Calgary, adjacent to an operating third-party natural gas facility.