National Grid invests $32 million to upgrade Buffalo Perry Street substation for 13,200-volt service
NGG•National Grid completed a $32 million modernization of its Perry Street substation in Buffalo, adding 13,200-volt distribution service to support projected electricity load growth.
1. Substation modernization
The upgrade adds 13,200-volt distribution delivery alongside the site’s legacy 4,160-volt service, supplying larger loads in Larkinville and the First Ward. The project went online this summer and is the first milestone in a multi-year reliability and resiliency plan; National Grid targets about a dozen Buffalo-area substations for modernization or rebuilding.