| 2021 OUTAGES | | | |
| Fluxys | Interconnector | Jul 6, 0600 CET - Mar 31, 2028 0600 CET | UK import capacity reduction to 31,392,673 kWh/h; unplanned equipment maintenance |
| 2025 OUTAGES | | | |
| INEOS | FPS system | 4Q (25 November) | Train 3 TAR has commenced with a current forecast duration of twelve (12) weeks |
| 2026 OUTAGES | | | |
| TAQA | UGS Bergermeer | Jul 13, 0400 CET - Jul 30, 0500 CET | 41 GWh/d; gas treatment plant unavailability |
| TAQA # | UGS Bergermeer | Jul 13, 0400 CET - Aug 12, 0400 CET | 38 GWh/d; compressor station unavailability |
| Gassco | St Fergus | Jun 08, 0600 CET - Aug 15, 0600 CET | 18.8 mcm/d; yearly maintenance |
| SSE | Aldbrough | Jun 10, 1800 BST - Jul 31, 1800 BST | 71.1 GWh/d; Unplanned injection unavailability |
| Gassco | Nyhamna | Jul 04, 0600 CET- Sep 24, 0600 CET | 19.8 mcm/d; planned corrective maintenance |
| Gassco | Nyhamna | Jul 04, 0600 CET - Sep 24, 0600 CET | 19.8 mcm/d; yearly maintenance |
| TAQA | UGS Bergermeer | Jul 19, 0400 CET - Aug 18, 0400 CET | 115 GWh/d; compression station unavailability |
| SSE | Aldbrough | Jul 26, 0500 BST - Jul 30, 1800 BST | 98 GWh/d; unplanned withdrawal unavailability |
| TAQA | UGS Bergermeer | Jul 30, 0400 CET - Aug 18, 0400 CET | 118 GWh/d; compression station unavailability |
| SSE | Aldbrough | Aug 03, 0500 BST - Aug 11, 1800 BST | 0.41 TWh; planned storage unavailability |
| Perenco | Bacton | Aug 01, 0600 BST - Aug 20, 0600 BST | 8.8 mcm/d; planned maintenance shutdown |
| TAQA | UGS Bergermeer | Aug 07, 0400 CET - Aug 18, 0500 CET | 118 GWh/d; compressor station unavailability |
| Total EP UK | Bacton SEAL (Elgin Franklin) | Aug 03, 0600 BST - Aug 07, 1200 BST | 4.4 mcm/d; Due to planned maintenance at the Bacton Terminal, Elgin Franklin exports will stop |
| TAQA # | UGS Bergermeer | Aug 12, 0400 BST - Aug 18, 0400 BST | 118 GWh/d; compressor station unavailability |
| SSE | Aldbrough | Aug 11, 0500 BST - Aug 20, 1800 BST | 0.41 TWh; planned storage unavailability |
| TAQA # | UGS Bergermeer | Aug 18, 0400 BST - Oct 03, 0400 BST | 185 GWh/d; Gas treatment plant unavailability |
| Gassco | Sleipner | Aug 28, 0600 CET - Sep 22, 0600 CET | 13.1 mcm/d; yearly maintenance |
| Gassco | Kollsnes | Aug 12, 0600 CET - Sep 22, 0600 CET | 16.0-40.0 mcm/d; yearly maintenance |
| Gassco | Troll | Aug 22, 0600 CET - Aug 23, 0600 CET | 8.4 mcm/d; yearly maintenance |
| NSMP | TGPP | Aug 23, 18 days | Planned Maintenance |
| Gassco | Troll | Aug 26, 0600 CET - Aug 28, 0600 CET | 10 mcm/d; yearly maintenance |
| Gassco | Kollsnes | Aug 29, 0600 CET - Sep 06, 0600 CET | 40 mcm/d; yearly maintenance |
| Gassco | Troll | Aug 29, 0600 CET - Sep 07, 0600 CET | 18 mcm/d; yearly maintenance |
| Scottish Power + | Hatfield | Apr 30, 0700 BST - Aug 31, 0500 BST | 20 GWh/d; planned withdrawal unavailability |
| Perenco | Bacton | Sep 01, 0600 BST - Sep 24, 0600 BST | 8 mcm/d; planned maintenance shutdown |
| Fluxys | Interconnector | Sep 01 - Sep 20 | Planned maintenance shutdown |
| Gassco | Easington | Sep 01, 0600 CET - Sep 02, 0600 CET | 42.7 mcm/d; yearly ESD test |
| SSE | Atwick | Sep 01, 0500 BST - Sep 08, 1800 BST | 30 GWh/d; Planned injection unavailability |
| Humbly Energy | Humbly Grove | Sep 02, 0500 BST - Sep 17, 0459 BST | 89 GWh/d; Annual Maintenance |
| Gassco | Troll | Sep 07, 0600 CET - Sep 19, 0600 CET | 13.2 mcm/d; yearly maintenance |
| Gassco | Kollsnes | Sep 06, 0600 CET - Sep 19, 0600 CET | 26.0 mcm/d; yearly maintenance |
| Gassco | Troll | Sep 21, 0600 CET - Sep 22, 0600 CET | 12.0 mcm/d; yearly maintenance |
| SSE | Aldbrough | Sep 12, 0500 BST - Sep 25, 1800 BST | 0.43 TWh; Planned Outage, Ald. 7 Maintenance & Intervention |
| Gassco | Aasta Hansteen | Sep 15, 0600 CET - Sep 17, 0600 CET | 16.1 mcm/d; yearly maintenance |
| Gassco | Nyhamna | Sep 15, 0600 CET - Sep 22, 0600 CET | 51.8 mcm/d; yearly maintenance |
| Gassco | Aasta Hansteen | Feb 13, 0600 CET - Sep 21, 0600 CET | 17.4 mcm/d; yearly maintenance |
| Gassco | Kollsnes | Sep 21, 0600 CET - Sep 22, 0600 CET | 40 mcm/d; yearly maintenance |
| Gassco | Kårstø | Sep 22, 0600 CET - Sep 26, 0600 CET | 19.6 mcm/d; yearly maintenance |
| Gassco | Aasta Hanstenn | Sep 23, 0600 CET - Sep 25, 0600 CET | 17.3 mcm/d; yearly maintenance |
| Gassco | Asgard | Sep 23, 0600 CET - Sep 24, 0600 CET | 26.9 mcm/d; yearly maintenance |
| Gassco | Kristin | Sep 23, 0600 CET - Sep 29, 0600 CET | 12.2 mcm/d; yearly maintenance |
| Gassco | Zeebrugge | Sep 21, 0600 CET - Sep 25, 0600 CET | 21.1 mcm/d upstrream restriction |
| Gassco | Skarv | Sep 23, 1328 CET - Sep 24, 0600 CET | 22.4 mcm/d; yearly maintenance |
| BBL company | BBL pipeline | Sep 30, 0600 CET - Oct 15, 0600 CET | Planned maintenance |
| Gassco | Oseberg | Sep 23, 0600 CET - Sep 30, 0600 CET | 13.5 mcm/d; yearly maintenance |
| Gassco | Aasta Hansteen | Sep 29, 0600 CET - Oct 03, 0600 CET | 17.7 mcm/d; yearly maintenance |
| TAQA | UGS Bergermeer | Sep 29, 0400 BST - Sep 30, 0400 BST | 41 GWh/d; other unavailability |
| Gassco | Zeebrugge | Sep 30, 0600 CET - Oct 01, 0600 CET | 22.2 mcm/d; yearly maintenance |
| TAQA # | UGS Bergermeer | Oct 03, 0500 CET - Oct 31, 0500 CET | 497 GWh/d; gas treatment plant unavailability |
| Gassco | Nyhamna | Oct 05, 0600 CET - Nov 02, 0600 CET | 19.8 mcm/d; yearly maintenance |
| Gassco | Oseberg | Oct 10, 0600 CET - Oct 23, 0600 CET | 27.5 mcm/d; yearly maintenance |
| Gassco | Aasta Hansteen | Oct 15, 0600 CET - Oct 19, 0600 CET | 20.7 mcm/d; yearly mainetenance |
| Kistos Energy Storage Ltd | Hill Top | Oct 22, 0800 BST - Oct 22, 1800 BST | 0.6477TWh; planned storage unavailability |
| SSE | Aldbrough | Oct 25, 0500 BST - Oct 31, 1800 BST | 97.78 GWh/d; planned injection unavailability |
| TAQA | UGS Bergermeer | Nov 11, 0500 BST - Nov 20, 0500 BST | 36 GWh/d; compression station unavailability |
| TAQA | UGS Bergermeer | Nov 20, 0500 BST - Dec 17, 0500 BST | 24 GWh/d; compression station unavailability |
| TAQA | UGS Bergermeer | Dec 16, 0500 BST - Dec 17, 0500 BST | 12 GWh/d; compressor station unavailability |
| Gassco | Visund | Dec 01, 0600 CET - Dec 02, 0600 CET | 14.8 mcm/d; yearly maintenance |
| INEOS | FPS system | 2026 | The annual Unity ESDV closure test, Cruden Bay NGL ESDV leak test, and Forties Charlie equipment tests will take place (3Q- Aug 4); the Old Lock Berth Outage will take place (2Q) |