RenX sets Microtec Turbo Mill at Florida organics facility, targets Q4 2026 commissioning
RENX•RenX installed its Microtec UTM 1200 Turbo Mill at its permitted 80-plus-acre organics processing site in Myakka City, Florida, with commissioning targeted for Q4 2026. The company said the mill could add a higher-margin product line; RenX reported $15 million in revenue for the 12 months ended June 30, 2026, and record Q2 revenue of $4.26 million.
1. Installation milestone
RenX Enterprises installed its Microtec UTM 1200 Turbo Mill at its permitted organics processing site in Myakka City, Florida. The project is the fourth of seven installation milestones, and commissioning remains on track for Q4 2026.
2. Remaining work and revenue
Remaining work centers on material handling integration, electrical interconnection and energization. RenX expects the mill to enable production of specification-grade engineered substrate from Florida organic material and add a higher-margin product line to a business that generated $15 million in revenue for the 12 months ended June 30, 2026; the company also reported record quarterly revenue of $4.26 million in Q2 2026.