TeraWulf expands Kentucky Power contract, doubles Muskie campus capacity to 1 GW
WULF•TeraWulf amended its electric service agreement with Kentucky Power, raising contracted capacity at its Muskie Data Campus to 1 GW. The second 500 MW phase is now scheduled for delivery in 2029, subject to Kentucky Public Service Commission approval, while the initial phase is slated to start ramping in 2028.
1. Capacity and schedule
TeraWulf executed an amended electric service agreement with Kentucky Power, increasing contracted capacity at its Muskie Data Campus to 1 GW. Delivery of the second 500 MW phase moved up to 2029 from 2030, subject to Kentucky Public Service Commission sign-off; the initial 500 MW phase remains slated to start ramping in 2028.