SSR Mining posts Marigold after-tax NPV5% of USD 3.3 billion in 20-year mine plan update
SSRM•SSR Mining’s updated 20-year plan for Nevada’s Marigold complex estimates an after-tax NPV5% of USD 3.3 billion, using consensus gold prices averaging USD 3,948 per ounce. Proven and probable reserves rose 43% to 4.63 million ounces, and the plan includes USD 542 million in growth capital.
1. Updated mine plan
SSR Mining released a 2026 technical report summary outlining a 20-year production plan for Nevada’s Marigold complex. The plan estimates an after-tax NPV5% of USD 3.3 billion using consensus gold prices averaging USD 3,948 per ounce over the mine life.
2. Reserves and production
Proven and probable reserves increased 43% to 4.63 million ounces from 3.2 million ounces at year-end 2025. Production is projected to average 231,000 ounces annually in 2027-2031, 201,000 ounces annually through 2040 and 169,000 ounces over the life of the mine. The plan adds Buffalo Valley, with 670,000 ounces of reserves; first production is targeted for 2029, and growth capital is budgeted at USD 542 million.