Suzano agrees to acquire 10% stake in Imetame Logística Porto via land contribution
SUZ•Project timeline and planned capacity
Imetame Logística is building a greenfield port hub; initial general cargo operations are targeted for early 2027.
The container terminal is expected to start in mid-2028, with capacity of about 1,200,000 TEUs a year and a 17-meter operational depth.
Financial impact and closing conditions
Suzano expects no material impact on its capital structure, and no capex is planned for 2026 tied to the stake.
Closing is subject to customary conditions, including regulatory approval.
Suzano to take 10% stake in port project
Suzano agreed to acquire a 10% stake in Imetame Logística Porto through a land contribution near Aracruz, Espírito Santo.