MDU Resources board reaches final investment decision for WBI Energy Bakken East Pipeline project
MDU•MDU Resources’ board reached a positive final investment decision to proceed with WBI Energy’s Bakken East pipeline, planned to carry 1.4 Bcf per day across about 350 miles. The project is estimated to cost $2.7 billion to $3.2 billion, with phased in-service targets in late 2029 and late 2030.
1. Project plans and costs
The pipeline is planned to run from western North Dakota to near Fargo, with construction scheduled across 2028–2030. The project includes expansions at existing compressor stations and four new stations; financing options are under review.